0000:00:00:00:00Start12Number 12ExplanationA team consists of 121212 people who can finish a job in 151515 days. If the job needs to be completed faster in 999 days, the percentage increase in workers needed to finish the job is...25.0%25.0\%25.0%37.5%37.5\%37.5%50.0%50.0\%50.0%62.5%62.5\%62.5%66.7%66.7\%66.7%