It is known that in a day Kardi can plaster 10 walls, while his colleague, Anton, can plaster 6 walls of the same size.
If Kardi and Anton work together to plaster 56 walls, the time required for both of them to complete the task is ... days.
Search for a command to run...
It is known that in a day Kardi can plaster 10 walls, while his colleague, Anton, can plaster 6 walls of the same size.
If Kardi and Anton work together to plaster 56 walls, the time required for both of them to complete the task is ... days.
We will calculate the combined work rate of Kardi and Anton, then determine the time needed to complete the total work.
Work rate of each person per day:
If they work together, their combined rate is:
The total work to be completed is 56 walls. The time required (t) can be calculated by dividing the total work by the combined rate.
We simplify the fraction:
So, the time required for both of them is 3.5 days.